APPENDIX

Block A – Opening of Windows in Front – 100% Done

Block B – Roof Beam Formwork and Reinforcement – 80% Done.

Block C- Blockwork on Cantilever slab – 100% Done.

Block D- Blockwork from Second Floor slab to Roof Beam Level -90% Done.
WORK PROGRESS
Block A.
- General electrical pipping work – 90%
- General Plumbing work – 90%
- Roof parapet work – 100%
- General internal plaster at A5-90%, A4 -90%, A3 -85%, A2 -85% A1 -90%
- General external plaster– 90%
- Blockwork on cantilever slab – 100%
- Copping Formwork and Reinforcement – In progress.
- Formwork and Reinforcement of Tile Beams – 100%
- Casting of Tie beams – In progress.
- Opening of windows in Front – 100%
Block B.
- Roof Beam Formwork and Reinforcement – 80%
- General Electrical work – 65%
- General plumbing work – 45%
- General Internal plastering – B1-50%, B2-0%, B3-45%, B4-30%, B5-30%
Block C.
- General Electrical Piping work – 90%
- General Plumbing work – 95%
- General internal plastering works C1-80%, C2-95%, C3-90%, C4-85%, C5-85%
- General external plastering – 95%
- Blockwork on Cantilever slab – 100%
- Formwork and Reinforcement of tie beams – 100%
- Casting of Tie beams – In progress.
- Opening of windows in Front – 100%
- Copping Formwork and Reinforcement – In progress.
Block D.
- Blockwork from Second Floor slab to Roof Beam Level – 90%
- Roof Beam formwork – 65%
- General Plumbing work – 40%
- General Electrical work – 40%
THANK YOU.