APPENDIX

Block A – Opening of Windows in Front – 100% Done

 

Block B – Roof Beam Formwork and Reinforcement – 80% Done.

 

Block C- Blockwork on Cantilever slab – 100% Done.

 

Block D- Blockwork from Second Floor slab to Roof Beam Level -90% Done.

 

WORK PROGRESS

Block A.

  • General electrical pipping work – 90%
  • General Plumbing work – 90%
  • Roof parapet work – 100%
  • General internal plaster at A5-90%, A4 -90%, A3 -85%, A2 -85% A1 -90%
  • General external plaster– 90%
  • Blockwork on cantilever slab – 100%
  • Copping Formwork and Reinforcement – In progress.
  • Formwork and Reinforcement of Tile Beams – 100%
  • Casting of Tie beams – In progress.
  • Opening of windows in Front – 100%

Block B.

  • Roof Beam Formwork and Reinforcement – 80%
  • General Electrical work – 65%
  • General plumbing work – 45%
  • General Internal plastering – B1-50%, B2-0%, B3-45%, B4-30%, B5-30%

Block C.

  • General Electrical Piping work – 90%
  • General Plumbing work – 95%
  • General internal plastering works C1-80%, C2-95%, C3-90%, C4-85%, C5-85%
  • General external plastering – 95%
  • Blockwork on Cantilever slab – 100%
  • Formwork and Reinforcement of tie beams – 100%
  • Casting of Tie beams – In progress.
  • Opening of windows in Front – 100%
  • Copping Formwork and Reinforcement – In progress.

Block D.

  • Blockwork from Second Floor slab to Roof Beam Level – 90%
  • Roof Beam formwork – 65%
  • General Plumbing work – 40%
  • General Electrical work – 40%

 

 

 

                                                                                     THANK YOU.