Phase 1 Report

APPENDIX

Picture showing the complete Roofing on Lot 15.

 

Retaining wall by the Gatehouse

 

Picture showing complete Roofing on Lot 15.

 

Picture showing the complete Roofing on Lot 11

 

Back filling on Lot 17 – 80% Done.

 

Picture showing All FD Staircase (Entrance) completed

 

FD – 9, 8, 7, 6, and 5 Soakaway block work and column completed.

 

Picture showing the Bridge.

 

Picture showing Stab reinforcement work on Lot 16

Picture showing the Park.

 

Picture showing the Gatehouse

 

WORK SUMMARY

 

LOT – 3:

  • Roofing – 100%
  • Parapet divider wall (Blockwork) – 60%

 

LOT – 4:

  • Bamboo scaffolding – 100%
  • Rafter – 100%
  • PPR piping – in progress.
  • Parapet divider wall (Blockwork) – 60%

LOT – 5: 

  • Internal rendering – 85%
  • Copping – 100%
  • Rafter – 100%
  • Parapet divider wall (Blockwork) – 60%

 

LOT – 6:

  • Internal rendering – 95%
  • Copping formwork completed.
  • Rafter – 100%
  • PPR piping – in progress.
  • Parapet divider wall (Blockwork) – 60%

LOT – 7:

  • Internal rendering – 95%
  • Rafter – 100%
  • PPR piping – in progress.
  • Parapet divider wall (Blockwork) – 60%.
  • Roofing – in progress.

 

LOT – 8:

  • Parapet divider wall (Blockwork) – 60%

 

 LOT- 11                                                                                                                                                                                                                                    

  • Copping – 100%
  • Internal rendering – 90%
  • Parapet divider wall (Blockwork) – 60%

 

LOT – 12:

  • Internal rendering – 95%
  • Copping – 100%
  • Roof trusses – 100%
  • Parapet divider wall (Blockwork) – 60%

 

LOT – 13

  • Copping – 100%
  • Internal rendering – 95%
  • Parapet divider wall (Blockwork) – 60%

LOT – 14:

  • External rendering – 100%
  • Internal rendering – 95%
  • Screeding – 100%
  • Copping – 100%
  • Roof trusses – 100%
  • Parapet divider wall (Blockwork) – 60%

 

LOT – 15

  • Copping – 100%
  • Internal rendering – 70%
  • Parapet divider wall (Blockwork) – 60%
  • PPR piping – in progress.

 

LOT – 16:

  • Slab formwork completed.
  • Reinforcement – 90%
  • Basement plastered.
  • First floor slab ready for Casting.

LOT – 17:

  • Basement stepdown 1 Backfilled.
  • Blockwork at 80% on stepdown 2.
  • Back filling – 80%

FD – 9, 8, 7, 6, and 5: Soakaway block work and column completed.

            GATEHOUSE:

  • Wall tiled.
  • Maintenance work ongoing.

RETAINING WALL:

  • By the Gatehouse – 85%
  • By the bridge to F-D 1 ongoing.

GENERAL WORKS

  • FD – 9 , 8, 7, 6, and 5: Soakaway block work and column completed.
  • Maintenance work ongoing.
  • All FD Staircase (Entrance) completed.

 

                                                     THANK YOU.