APPENDIX

Block A – Plastering of Parapet walls and Dressing of coping – 80% Done

Block B – Blockwork above Roof Beam – In progress.

Block C- Parapet Blockwork– 100% Done.

Block D- Casting of Roof Beam – 80% Done.
WORK PROGRESS
Block A.
- General electrical pipping work – 90%
- General Plumbing work – 90%
- General internal plaster at A1-90%, A2 -90%, A3 -85%, A4 -90%, A5 -90%
- General external plaster– 90%
- Parapet Blockwork – 100%
- Casting of coping – 100%
- Plastering of Parapet walls and Dressing of coping – 80%
- Internal Blockwork to Roof level – In progress.
Block B.
- Casting of Roof Beam – 100%
- General Electrical work – 70%
- General plumbing work – 70%
- General Internal plastering – B1-65%, B2-0%, B3-55%, B4-50%, B5-45%
- Blockwork above Roof Beam – In progress.
- Columns Extension – 100%
Block C.
- General Electrical Piping work – 90%
- General Plumbing work – 95%
- General Internal plastering – C1-85%, C2-95%, C3-90%, C4-85%, C5-85%
- General External plastering – 80%
- Parapet Blockwork – 100%
- Casting of coping – 100%
- Plastering of parapet walls and Dressing of coping – 90%
- Internal Blockwork to Roof level – In progress.
Block D.
- Casting of Roof Beam – 80%
- General Plumbing work – 55%
- General Electrical work – 40%
THANK YOU.