Block A – Roof trusses – 90% done.

Block B Blockwork above Roof Beam – 100% done.

Block CRoof trusses work– 90% done.

Picture showing the Excavation on Lot 18, 19, and 20.

Block D- Blockwork above Roof Beam – 70% done.

WORK PROGRESS

Block A.

  • General Electrical pipping work – 90%
  • General Plumbing work – 90%
  • General internal plaster at A1-90%, A2 -90%, A3 -90%, A4 -90%, A5 -95%
  • General External plaster– 95%
  • Plastering of Parapet walls and Dressing of coping – 90%
  • Internal Blockwork to Roof level – 100%
  • Plastering of internal blockwork to Roof level – 20%
  • Roof trusses – 90%

Block B.

  • General Electrical work – 75%
  • General plumbing work – 85%
  • General Internal plastering – B1-90%, B2-30%, B3-70%, B4-65%, B5-90%
  • General External plastering – 20%
  • Blockwork above Roof beam – 100%
  • Cantilever in front formwork – completed
  • Reinforcement of cantilever – 100%
  • Formwork to tie beams at sides – 100%
  • Tie beams reinforcement – 100%

Block C.

  • General Electrical Piping work – 90%
  • General Plumbing work – 95%
  • General Internal plastering – C1-90%, C2-95%, C3-95%, C4-90%, C5-90%
  • General External plastering – 80%
  • Plastering of parapet walls and Dressing of coping – 90%
  • Internal Blockwork to Roof level – 100%
  • Plastering of internal blockwork done to roof level – 95%
  • Roof trusses – 90%

Block D.

  • External scaffolding – 50%
  • Casting of Roof Beams – 80%
  • Blockwork above roof beam – 70%
  • General plumbing work – 75%
  • General Electrical work – 50%
  • Formwork for cantilever – In progress
  • General internal plastering – D1- 20%, D2 – 45%, D3 -25%, D4 -25%, D5 -25%

THANK YOU.