Block A – Roof trusses – 90% done.
Block B – Blockwork above Roof Beam – 100% done.
Block C– Roof trusses work– 90% done.
Picture showing the Excavation on Lot 18, 19, and 20.
Block D- Blockwork above Roof Beam – 70% done.
WORK PROGRESS
Block A.
- General Electrical pipping work – 90%
- General Plumbing work – 90%
- General internal plaster at A1-90%, A2 -90%, A3 -90%, A4 -90%, A5 -95%
- General External plaster– 95%
- Plastering of Parapet walls and Dressing of coping – 90%
- Internal Blockwork to Roof level – 100%
- Plastering of internal blockwork to Roof level – 20%
- Roof trusses – 90%
Block B.
- General Electrical work – 75%
- General plumbing work – 85%
- General Internal plastering – B1-90%, B2-30%, B3-70%, B4-65%, B5-90%
- General External plastering – 20%
- Blockwork above Roof beam – 100%
- Cantilever in front formwork – completed
- Reinforcement of cantilever – 100%
- Formwork to tie beams at sides – 100%
- Tie beams reinforcement – 100%
Block C.
- General Electrical Piping work – 90%
- General Plumbing work – 95%
- General Internal plastering – C1-90%, C2-95%, C3-95%, C4-90%, C5-90%
- General External plastering – 80%
- Plastering of parapet walls and Dressing of coping – 90%
- Internal Blockwork to Roof level – 100%
- Plastering of internal blockwork done to roof level – 95%
- Roof trusses – 90%
Block D.
- External scaffolding – 50%
- Casting of Roof Beams – 80%
- Blockwork above roof beam – 70%
- General plumbing work – 75%
- General Electrical work – 50%
- Formwork for cantilever – In progress
- General internal plastering – D1- 20%, D2 – 45%, D3 -25%, D4 -25%, D5 -25%
THANK YOU.