Picture showing the complete Roofing on Lot 15.

Completed Roofing on Lot 4-6.

Picture showing Profile Level on Lot 21 & 22.

Picture showing the Excavation on Lot 18, 19, and 20.

Ground floor level hardcore laying on Lot 17 ongoing.

Road (Earthwork) between Lot 11, 12 and 14, 15 ongoing.

FDs Road (Earthwork) ongoing.

Picture showing the Bridge.

Slab blockwork on Lot 16, 40% done.

Picture showing the Park.

Picture showing the Gatehouse.
WORK SUMMARY
LOT – 3:
- Roofing – 100%
- Parapet divider wall (Blockwork) – 60%
LOT – 4:
- Bamboo scaffolding – 100%
- Rafter – 100%
LOT – 5:
- Internal rendering – 85%
- Copping – 100%
- Rafter – 100%
LOT – 6:
- Internal rendering – 95%
- Copping formwork
- Rafter – 100%
LOT – 7:
- Internal rendering – 95%
- Rafter – 100%
- PPR piping – in
- Parapet divider wall (Blockwork) – 60%.
- Roofing – in
LOT – 8:
- Parapet divider wall (Blockwork) – 60%
LOT – 11:
- Copping – 100%
- Internal rendering – 90%
- Parapet divider wall (Blockwork) – 60%
LOT – 12:
- Internal rendering – 95%
- Copping – 100%
- Roof trusses – 100%
- Parapet divider wall (Blockwork) – 60%
LOT – 13
- Copping – 100%
- Internal rendering – 95%
- Parapet divider wall (Blockwork) – 60%
LOT – 14:
- External rendering – 100%
- Internal rendering – 95%
- Screeding – 100%
- Copping – 100%
- Roof trusses – 100%
- Parapet divider wall (Blockwork) – 60%
LOT – 15
- Copping – 100%
- Internal rendering – 70%
- Parapet divider wall (Blockwork) – 60%
- PPR piping – in
LOT – 16:
- Slab formwork
- Reinforcement – 90%
- Basement
- First-floor slab ready for
- Slab blockwork – 40%
LOT – 17:
- Basement stepdown 1
- Blockwork at 80% on stepdown
- Backfilling – 80%
- Ground floor level hardcore laying
LOT – 21 & 22:
- At profile
FD – 9, 8, 7, 6, and 5: Soakaway block work and column completed.
GATEHOUSE:
- Wall
- Maintenance work – 90%
RETAINING WALL:
- By the Gatehouse – 85%
- By the bridge to F-D 1
GENERAL WORKS
- FD – 9, 8, 7, 6, and 5: Soakaway block work and column
- Road (Earthwork)
- The road along the Bridge, in between Lot 11, 12 and 14, 15, FDs road ongoing.
- Perimeter Fencing
- Lot 18, 19, and 20:
THANK YOU.