Fixing/installation of windows 100% done on Block A.
External wall screeding – In view on Block B.
Fixing of wall skirting’s and Grooves -90% done on Block C.
Window dressings and fixing of window grooves 100% done on Block D.
External wall screeding – 10% done on Block E.
Picture showing the POP on Block D.
WORK SUMMARY
BLOCK A
- Fixing of electrical cables (Wiring) –
- Installation of Pop (Polysterene) Ceiling –
- External wall screeding – 10% done.
- External wall painting – In view.
BLOCK B
- Fixing of Electrical cables (Wiring) –
- Plastering of Internal wall – 90%
- Fixing of wall skirtings and window Grooves – 100%
- Installation of Pop (polysterene) Ceiling – 45%
- Fixing/installation of windows – 80%
- External wall screeding – In view.
BLOCK C
- Fixing of wall skirting’s and Grooves – 90%
- Window Dressings and fixing of window Grooves – 40%
- Fixing of Electrical cables (wiring) – 60%
- Installation of Pop (Polysterene) Ceiling – 20%
- External wall screeding – In view.
BLOCK D
- Fixing of electrical cables (Wiring) –
- Installation of Pop (Polysterene) Ceiling – 75%
- Window Dressings and fixing of windows Grooves – 100%
- External wall screeding – 10% done.
- External wall Painting – In
BLOCK E
- Plastering of Internal wall – 100%
- Window Dressings and Fixing of window Grooves – 100%
- External wall screeding – 10%
- Installation of POP Ceiling – In
SUMMARY OF STATE OF WORK
- Plastering of internal wall 100% done on Block
- Setting of partition wall 100% done on Block B
- Roof trusses installation 100% done Block
- Formwork and shuttering to third floor slab 100% done on Block
- Reinforcement to third floor slab 100% done on Block
- Plumbing works on each floor 100% done on Block
- Roofing (step tiles installation) 100% done on Block