APPENDIX

Block A – First floor slab beam and staircase concrete works 100% done.

Block B – First floor block work – 100% done.

Block C – Formwork for first floor slab, Beam and Staircase – 55% done.

Block D – Formwork for second floor slab, beam and staircase – 40% done.

Block E – First floor block work – 98% done.

Block F – Reinforcement for first floor slab, Beam and Staircase 100% done.

WORK PROGRESS

BLOCK A

  • Block work for ground floor – 100%
  • Formwork for first floor slab, beam and staircase – 100%
  • Reinforcements for first floor slab, beam and staircase – 100%
  • Electrical piping on first floor slab – 100%
  • Plumbing piping on first floor slab – 100%
  • First floor slab beam and staircase concrete works – 100%
  • Reinforcement for first floor extension columns – 100%
  • First floor block work – 95%
  • Formwork for first floor extension columns/lintels – 100%
  • Concrete works on first floor extension columns/lintels – 100%

BLOCK B

  • Block work for ground floor – 100%
  • Formwork for first floor slab, beam and staircase – 100%
  • Reinforcements for first floor slab, beam and staircase – 100%
  • Electrical piping on first floor slab – 100%
  • Plumbing piping on first floor slab – 100%
  • First floor slab beam and staircase concrete works – 100%
  • Reinforcement for first floor extension columns – 100%
  • First floor block work – 100%
  • Formwork for first floor extension columns/lintels – 100%
  • Concrete works on first floor extension columns/lintels – 100%

BLOCK C

  • Blockwork for ground floor – 100% done.
  • Formwork for first floor slab, Beam and Staircase – 55%
  • Reinforcements for slab, Beam and Staircase – (To be commence).
  • Electrical piping on first floor slab – (To be commence).
  • Plumbing piping on first floor slab – (To be commence).

BLOCK D

  • Block work for ground floor – 100%
  • Formwork for first floor slab, beam and staircase – 100%
  • Reinforcements for first floor slab, beam and staircase – 100%
  • Electrical piping on first floor slab – 100%
  • Plumbing piping on first floor slab – 100%
  • First floor slab beam and staircase concrete works – 100%
  • Reinforcement for 1st floor extension columns/lintels – 100%
  • First floor block work – 85%
  • Formwork for first floor extension columns/lintels – 100%
  • Concrete works on first floor extension columns/lintels – 100%
  • Formwork for second floor slab, beam and staircase – 40%

BLOCK E

  • Block work for ground floor – 100%
  • Formwork for first floor slab, beam and staircase – 100%
  • Reinforcements for first floor slab, beam and staircase 100%
  • Electrical piping on first floor slab – 100%
  • Plumbing piping on first floor slab – 100%
  • First floor slab beam and staircase concrete works – 100%
  • Reinforcement for first floor extension columns/lintels – 100%
  • First floor block work – 98%
  • Formwork for first floor extension columns/lintels – 100%
  • Concrete works on first floor extension columns/lintels – 100%

BLOCK F

  • Blockwork for ground floor – 100%
  • Formwork for first floor slab, Beam and Staircase – 100%
  • Reinforcement for first floor slab, Beam and Staircase – 100%
  • Electrical piping on first floor slab – 100%
  • Plumbing piping on first floor slab – 100%
  • First floor slab beam and staircase concrete works – 100%
  • Reinforcement for first floor extension columns/lintels – 100%
  • First floor block work – 99%
  • Formwork for first floor extension columns/lintels – 100%
  • Concrete works on first floor extension columns/lintels – 100%

THANK YOU.