APPENDIX
Block A – First floor slab beam and staircase concrete works 100% done.
Block B – First floor block work – 100% done.
Block C – Formwork for first floor slab, Beam and Staircase – 55% done.
Block D – Formwork for second floor slab, beam and staircase – 40% done.
Block E – First floor block work – 98% done.
Block F – Reinforcement for first floor slab, Beam and Staircase 100% done.
WORK PROGRESS
BLOCK A
- Block work for ground floor – 100%
- Formwork for first floor slab, beam and staircase – 100%
- Reinforcements for first floor slab, beam and staircase – 100%
- Electrical piping on first floor slab – 100%
- Plumbing piping on first floor slab – 100%
- First floor slab beam and staircase concrete works – 100%
- Reinforcement for first floor extension columns – 100%
- First floor block work – 95%
- Formwork for first floor extension columns/lintels – 100%
- Concrete works on first floor extension columns/lintels – 100%
BLOCK B
- Block work for ground floor – 100%
- Formwork for first floor slab, beam and staircase – 100%
- Reinforcements for first floor slab, beam and staircase – 100%
- Electrical piping on first floor slab – 100%
- Plumbing piping on first floor slab – 100%
- First floor slab beam and staircase concrete works – 100%
- Reinforcement for first floor extension columns – 100%
- First floor block work – 100%
- Formwork for first floor extension columns/lintels – 100%
- Concrete works on first floor extension columns/lintels – 100%
BLOCK C
- Blockwork for ground floor – 100% done.
- Formwork for first floor slab, Beam and Staircase – 55%
- Reinforcements for slab, Beam and Staircase – (To be commence).
- Electrical piping on first floor slab – (To be commence).
- Plumbing piping on first floor slab – (To be commence).
BLOCK D
- Block work for ground floor – 100%
- Formwork for first floor slab, beam and staircase – 100%
- Reinforcements for first floor slab, beam and staircase – 100%
- Electrical piping on first floor slab – 100%
- Plumbing piping on first floor slab – 100%
- First floor slab beam and staircase concrete works – 100%
- Reinforcement for 1st floor extension columns/lintels – 100%
- First floor block work – 85%
- Formwork for first floor extension columns/lintels – 100%
- Concrete works on first floor extension columns/lintels – 100%
- Formwork for second floor slab, beam and staircase – 40%
BLOCK E
- Block work for ground floor – 100%
- Formwork for first floor slab, beam and staircase – 100%
- Reinforcements for first floor slab, beam and staircase 100%
- Electrical piping on first floor slab – 100%
- Plumbing piping on first floor slab – 100%
- First floor slab beam and staircase concrete works – 100%
- Reinforcement for first floor extension columns/lintels – 100%
- First floor block work – 98%
- Formwork for first floor extension columns/lintels – 100%
- Concrete works on first floor extension columns/lintels – 100%
BLOCK F
- Blockwork for ground floor – 100%
- Formwork for first floor slab, Beam and Staircase – 100%
- Reinforcement for first floor slab, Beam and Staircase – 100%
- Electrical piping on first floor slab – 100%
- Plumbing piping on first floor slab – 100%
- First floor slab beam and staircase concrete works – 100%
- Reinforcement for first floor extension columns/lintels – 100%
- First floor block work – 99%
- Formwork for first floor extension columns/lintels – 100%
- Concrete works on first floor extension columns/lintels – 100%
THANK YOU.