APPENDIX

Block A – External work/Landscaping – 80% done.

Block B – Tiling works – 60% done.

Block C – External work/Landscaping/Infrastructure – 80% done.

Block D – External wall painting – 100% done

Block E – External work/Landscaping/Infrastructure – 80% done.

WORK PROGRESS

BLOCK A

  • External wall painting – 100% done.
  • Tiling works – In view.
  • External work/Landscaping/Infrastructure – 80% done.

BLOCK B

  • Installation of Pop ceiling – 100% done.
  • External wall painting – 100% done.
  • Tiling works – 60% done.
  • Internal woodwork/Furniture/Cabinets – 30% done.
  • External work/Landscaping/Infrastructure – 80% done.
  • Internal wall screeding – 60% done.
  • Internal wall painting – In view.

BLOCK C

  • Installation of Pop ceiling – 60% done
  • Tiling works – 20% done.
  • External wall painting – 100%
  • External work/Landscaping/Infrastructure – 80% done.
  • Internal wall screeding – 10% done.

BLOCK D

  • Installation of Pop ceiling – 90% done.
  • External wall painting – 100% done.
  • Tiling works – 70% done.
  • Internal wall screeding – 60% done.
  • Internal woodwork/Furniture/Cabinets – 30%
  • External work/Landscaping/Infrastructure – 80% done.
  • Internal wall painting – In view

BLOCK E

  • Installation of Pop ceiling – 60% done
  • Tiling works – 60% done.
  • External wall painting – 100%
  • External work/Landscaping/Infrastructure – 80% done.
  • Internal wall screeding – In view.

THANK YOU.