APPENDIX

Block A – External work/Landscaping – 80% done.

Block B – Tiling works – 60% done.

Block C – External work/Landscaping/Infrastructure – 80% done.

Block D – External wall painting – 100% done

Block E – External work/Landscaping/Infrastructure – 80% done.
WORK PROGRESS
BLOCK A
- External wall painting – 100% done.
- Tiling works – In view.
- External work/Landscaping/Infrastructure – 80% done.
BLOCK B
- Installation of Pop ceiling – 100% done.
- External wall painting – 100% done.
- Tiling works – 60% done.
- Internal woodwork/Furniture/Cabinets – 30% done.
- External work/Landscaping/Infrastructure – 80% done.
- Internal wall screeding – 60% done.
- Internal wall painting – In view.
BLOCK C
- Installation of Pop ceiling – 60% done
- Tiling works – 20% done.
- External wall painting – 100%
- External work/Landscaping/Infrastructure – 80% done.
- Internal wall screeding – 10% done.
BLOCK D
- Installation of Pop ceiling – 90% done.
- External wall painting – 100% done.
- Tiling works – 70% done.
- Internal wall screeding – 60% done.
- Internal woodwork/Furniture/Cabinets – 30%
- External work/Landscaping/Infrastructure – 80% done.
- Internal wall painting – In view
BLOCK E
- Installation of Pop ceiling – 60% done
- Tiling works – 60% done.
- External wall painting – 100%
- External work/Landscaping/Infrastructure – 80% done.
- Internal wall screeding – In view.