APPENDIX

Scaffold mounting – 100% done.
WORK PROGRESS
- Roof truss forming for main building and security house – 100%
- Scaffold mounting – 100%
- Exterior Plastering – 80%
- External Electrical works – 100%
- External plumbing works – 100%.
- Fence Electrical piping – 50%
CONCLUSION: Work is in progress using the best quality in every items of work and making sure that the project will be completed in stipulated time.
THANK YOU.