APPENDIX

F-D: Asphalt work – 100% done.

Arial view of 4 bedroom, 3 bedroom and their Road network.

Picture showing the Bridge.

Lot – 16: Roof beam formwork – 100% done.
WORK SUMMARY
LOT – 16:
- Roof beam formwork – 100%
- Parapet blockwork – 100%
- Bamboo scaffolding – 90%
- Copping – 100%
- Plastering of the whole block – in progress.
LOT – 17:
- Slab formwork – 100%
- reinforcement to the slab
- Preparation for the casting of the slab.
ALL F-Ds:
- All Screeded.
- Roadwork stone base completed
- Asphalt work – 100% done.
Cesspool construction in progress.
THANK YOU.