APPENDIX

F-D: Asphalt work – 100% done.

Arial view of 4 bedroom, 3 bedroom and their Road network.

Picture showing the Bridge.

Lot – 16: Roof beam formwork – 100% done.

WORK SUMMARY

LOT – 16:

  • Roof beam formwork – 100%
  • Parapet blockwork – 100%
  • Bamboo scaffolding – 90%
  • Copping – 100%
  • Plastering of the whole block – in progress.

LOT – 17:

  • Slab formwork – 100%
  • reinforcement to the slab
  • Preparation for the casting of the slab.

ALL F-Ds:

  • All Screeded.
  • Roadwork stone base completed
  • Asphalt work – 100% done.

Cesspool construction in progress.

THANK YOU.