APPENDIX

Block A – External works/Landscaping/Infrastructure – 90% done.

Block B – Tiling works – 85% done.

Block C – External work/Landscaping/Infrastructure – 100% done.

Block D – External wall painting – 100% done

Block E – External work/Landscaping/Infrastructure – 100% done.

WORK PROGRESS

BLOCK A

  • Tiling works – 10%
  • External works/Landscaping/Infrastructure – 90% done.
  • Installation of Balustrade/General steel works – 60%
  • Fixing of electrical cables (Internal wiring) – 40%
  • Installation of POP ceiling – In view.

BLOCK B

  • Tiling works – 85% done.
  • Installation woodwork railings/general steel works – 90%
  • Internal woodwork/Furniture/Cabinets – 70% done.
  • External works/Landscaping/Infrastructure – 100% done.
  • Internal wall screeding – 80%
  • Internal wall painting – In view.

BLOCK C

  • Installation of Pop ceiling – 70% done
  • Tiling works – 40% done.
  • External works/Landscaping/Infrastructure – 100% done.
  • Internal wall screeding – 30% done.
  • Internal woodwork/Furniture/Cabinets – 10% done.

BLOCK D

  • Installation of Pop ceiling – 90% done.
  • Tiling works – 85% done.
  • Internal wall screeding – 80% done.
  • Internal woodwork/Furniture/Cabinets – 60%
  • External works/Landscaping/Infrastructure – 100% done.
  • Internal wall painting – In view
  • Installation of Balustrade/General steel works – 100%

BLOCK E

  • Installation of Pop ceiling – 60% done
  • Tiling works – 30% done.
  • External works/Landscaping/Infrastructure – 100% done.
  • Installation of Balustrade/General steel works – 100%
  • Internal wall screeding – 20%
  • Internal wall painting – In view.