APPENDIX

Block A – External works/Landscaping/Infrastructure – 90% done.

Block B – Tiling works – 85% done.

Block C – External work/Landscaping/Infrastructure – 100% done.

Block D – External wall painting – 100% done

Block E – External work/Landscaping/Infrastructure – 100% done.
WORK PROGRESS
BLOCK A
- Tiling works – 10%
- External works/Landscaping/Infrastructure – 90% done.
- Installation of Balustrade/General steel works – 60%
- Fixing of electrical cables (Internal wiring) – 40%
- Installation of POP ceiling – In view.
BLOCK B
- Tiling works – 85% done.
- Installation woodwork railings/general steel works – 90%
- Internal woodwork/Furniture/Cabinets – 70% done.
- External works/Landscaping/Infrastructure – 100% done.
- Internal wall screeding – 80%
- Internal wall painting – In view.
BLOCK C
- Installation of Pop ceiling – 70% done
- Tiling works – 40% done.
- External works/Landscaping/Infrastructure – 100% done.
- Internal wall screeding – 30% done.
- Internal woodwork/Furniture/Cabinets – 10% done.
BLOCK D
- Installation of Pop ceiling – 90% done.
- Tiling works – 85% done.
- Internal wall screeding – 80% done.
- Internal woodwork/Furniture/Cabinets – 60%
- External works/Landscaping/Infrastructure – 100% done.
- Internal wall painting – In view
- Installation of Balustrade/General steel works – 100%
BLOCK E
- Installation of Pop ceiling – 60% done
- Tiling works – 30% done.
- External works/Landscaping/Infrastructure – 100% done.
- Installation of Balustrade/General steel works – 100%
- Internal wall screeding – 20%
- Internal wall painting – In view.