APPENDIX
F-Ds: Roadwork stone base completed.
Picture showing the Bridge.
Arial view of 4 bedroom, 3 bedroom and their Road network.
Lot – 16: Plastering of the whole block – in progress.
Lot – 18-22: Foundation to DPC.
Lot – 32-33: Foundation to DPC.
Lot – 17: Reinforcement to first floor – 100% done.
Transformer located already and connection to building in progress.
WORK SUMMARY
LOT – 16:
- Roof beam formwork – 100%
- Parapet blockwork – 100%
- External plastering – 100%
- Plastering of the whole block – in progress.
LOT – 17:
- Slab formwork – 100%
- Reinforcement to first floor – 100%
LOT – 18 -22:
- Foundation to DPC
- Blockwork to first floor in progress.
LOT – 23, 29, 30:
- Foundation to DPC
LOT – 25, 26, 31:
- Foundation to DPC
- Blockwork to first floor in progress
LOT – 32, & 33:
- Foundation to DPC
ALL F-Ds:
- All Screeded.
- Roadwork stone base completed
- Asphalt work – 100% done.
Cesspool construction in progress.
Transformer located already and connection to building in progress.
THANK YOU.