APPENDIX

F-Ds: Roadwork stone base completed.

Picture showing the Bridge.

Arial view of 4 bedroom, 3 bedroom and their Road network.

Lot – 16: Plastering of the whole block – in progress.

Lot – 18-22: Foundation to DPC.

Lot – 32-33: Foundation to DPC.

Lot – 17: Reinforcement to first floor – 100% done.

Transformer located already and connection to building in progress.

WORK SUMMARY

LOT – 16:

  • Roof beam formwork – 100%
  • Parapet blockwork – 100%
  • External plastering – 100%
  • Plastering of the whole block – in progress.

LOT – 17:

  • Slab formwork – 100%
  • Reinforcement to first floor – 100%

LOT – 18 -22:

  • Foundation to DPC
  • Blockwork to first floor in progress.

LOT – 23, 29, 30:

  • Foundation to DPC

LOT – 25, 26, 31:

  • Foundation to DPC
  • Blockwork to first floor in progress

LOT – 32, & 33:

  • Foundation to DPC

ALL F-Ds:

  • All Screeded.
  • Roadwork stone base completed
  • Asphalt work – 100% done.

Cesspool construction in progress.

Transformer located already and connection to building in progress.

THANK YOU.