APPENDIX

Lot 1 – Slab formwork to first floor – 100% done.

Lot 2 – Formwork for Slab on first floor – 70% work in progress.

Lot 3 Blockwork at Ground floor completed – 100% done.

Lot 4 – Slab Reinforcement on ground floor completed- 100% done.

Lot 5 – Slab Reinforcement / wood formwork completed – 100% done.

WORK PROGRESS

Lot 1

  • Mechanical work – 80% work in progress.
  • Electrical work – 40% work in progress.
  • Slab Reinforcement on first floor – 100% work in progress.
  • Slab formwork to first floor – 100%.
  • Blockwork @ Basement completed – 100%
  • Blockwork on Ground Floor completed – 100%

Lot 2

  • Formwork for Slab on first floor- 70% work in progress.
  • Block work at first Floor completed – 100%
  • Block work on ground floor completed – 100%
  • Plumbing / Mechanical – 80%

Lot 3

  • Blockwork on first floor – 100% work in progress.
  • Slab Reinforcement on Ground floor – 100%
  • Plumbing /mechanical – 100%
  • Electrical -100%
  • Blockwork at Ground floor completed -100%

Lot 4

  • Block work – 50% work in progress.
  • Slab Reinforcement on ground floor completed- 100%
  • Mechanical fittings completed- 100%.
  • Electrical fittings- 90% work in progress.
  • Slab formwork on Ground floor – 50% work in progress.
  • Block work on ground floor completed -100%

Lot 5

  • Blockwork on first floor – 100% work in progress.
  • Slab Reinforcement / wood formwork completed – 100%
  • Mechanical work- 100%
  • Electrical – 100%
  • Blockwork on ground floor completed – 100%