APPENDIX
Lot 1 – Slab formwork to first floor – 100% done.
Lot 2 – Formwork for Slab on first floor – 70% work in progress.
Lot 3 – Blockwork at Ground floor completed – 100% done.
Lot 4 – Slab Reinforcement on ground floor completed- 100% done.
Lot 5 – Slab Reinforcement / wood formwork completed – 100% done.
WORK PROGRESS
Lot 1
- Mechanical work – 80% work in progress.
- Electrical work – 40% work in progress.
- Slab Reinforcement on first floor – 100% work in progress.
- Slab formwork to first floor – 100%.
- Blockwork @ Basement completed – 100%
- Blockwork on Ground Floor completed – 100%
Lot 2
- Formwork for Slab on first floor- 70% work in progress.
- Block work at first Floor completed – 100%
- Block work on ground floor completed – 100%
- Plumbing / Mechanical – 80%
Lot 3
- Blockwork on first floor – 100% work in progress.
- Slab Reinforcement on Ground floor – 100%
- Plumbing /mechanical – 100%
- Electrical -100%
- Blockwork at Ground floor completed -100%
Lot 4
- Block work – 50% work in progress.
- Slab Reinforcement on ground floor completed- 100%
- Mechanical fittings completed- 100%.
- Electrical fittings- 90% work in progress.
- Slab formwork on Ground floor – 50% work in progress.
- Block work on ground floor completed -100%
Lot 5
- Blockwork on first floor – 100% work in progress.
- Slab Reinforcement / wood formwork completed – 100%
- Mechanical work- 100%
- Electrical – 100%
- Blockwork on ground floor completed – 100%