APPENDIX

Block A – First floor block work – 95% done.

Block B – Ground floor internal plastering – 80% done.

Block C – Formwork for first floor slab, Beam and Staircase – 90% done.

Block D – Ground floor internal plastering – 80% done.

Block E – First floor block work – 98% done.

Block F – Reinforcement for first floor slab, Beam and Staircase 100% done.

WORK PROGRESS

BLOCK A
  • Block work for ground floor – 100%
  • Formwork for first floor slab, beam and staircase – 100%
  • Reinforcements for first floor slab, beam and staircase – 100%
  • Electrical piping on first floor slab – 100%
  • Plumbing piping on first floor slab – 100%
  • First floor slab beam and staircase concrete works – 100%
  • Reinforcement for first floor extension columns – 100%
  • First floor block work – 95%
  • Formwork for first floor extension columns/lintels – 100%
  • Concrete works on first floor extension columns/lintels – 100%
BLOCK B
  • Block work for ground floor – 100%
  • Formwork for first floor slab, beam and staircase – 100%
  • Reinforcements for first floor slab, beam and staircase – 100%
  • Electrical piping on first floor slab – 100%
  • Plumbing piping on first floor slab – 100%
  • First floor slab beam and staircase concrete works – 100%
  • Reinforcement for first floor extension columns – 100%
  • First floor block work – 100%
  • Formwork for first floor extension columns/lintels – 100%
  • Concrete works on first floor extension columns/lintels – 100%
  • Ground floor internal plastering – 80%
BLOCK C
  • Blockwork for ground floor – 100% done.
  • Formwork for first floor slab, Beam and Staircase – 90% done.
  • Reinforcements for slab, Beam and Staircase – (To be commence).
  • Electrical piping on first floor slab – (To be commence).
  • Plumbing piping on first floor slab – (To be commence).
BLOCK D
  • Block work for ground floor – 100%
  • Formwork for first floor slab, beam and staircase – 100%
  • Reinforcements for first floor slab, beam and staircase – 100%
  • Electrical piping on first floor slab – 100%
  • Plumbing piping on first floor slab – 100%
  • First floor slab beam and staircase concrete works – 100%
  • Reinforcement for first floor extension columns/lintels – 100%
  • First floor block work – 100%
  • Formwork for first floor extension columns/lintels – 100%
  • Concrete works on first floor extension columns/lintels – 100%
  • Formwork for second floor slab, beam and staircase – 85%
  • Ground floor internal plastering – 80%

 

BLOCK E

  • Block work for ground floor – 100%
  • Formwork for first floor slab, beam and staircase – 100%
  • Reinforcements for first floor slab, beam and staircase – 100%
  • Electrical piping on first floor slab – 100%
  • Plumbing piping on first floor slab – 100%
  • First floor slab beam and staircase concrete works – 100%
  • Reinforcement for first floor extension columns/lintels – 100%
  • First floor block work – 99%
  • Formwork for first floor extension columns/lintels – 100%
  • Concrete works on first floor extension columns/lintels – 100%

BLOCK F

  • Blockwork for ground floor – 100%
  • Formwork for first floor slab, Beam and Staircase – 100%
  • Reinforcement for first floor slab, Beam and Staircase – 100%
  • Electrical piping on first floor slab – 100%
  • Plumbing piping on first floor slab – 100%
  • First floor slab beam and staircase concrete works – 100%
  • Reinforcement for first floor extension columns/lintels – 100%
  • First floor block work – 99%
  • Formwork for first floor extension columns/lintels – 100%
  • Concrete works on first floor extension columns/lintels – 100%

                                                             