APPENDIX

Block A – Formwork for first floor extension columns/lintels – 100% done.

Block B – First floor block work – 100% done.

Block C – Formwork for first floor slab, Beam and Staircase – 97% done.

Block D – Reinforcements for second floor slab, beam and staircase – 100% done.

Block E – First floor block work – 99% done.

Block F – Concrete works on first floor extension columns/lintels – 100% done.
WORK PROGRESS
BLOCK A
- Block work for ground floor – 100%
- Formwork for first floor slab, beam and staircase – 100%
- Reinforcements for first floor slab, beam and staircase – 100%
- Electrical piping on first floor slab – 100%
- Plumbing piping on first floor slab – 100%
- First floor slab beam and staircase concrete works – 100%
- Reinforcement for first floor extension columns – 100%
- First floor block work – 97%
- Formwork for first floor extension columns/lintels – 100%
- Concrete works on first floor extension columns/lintels – 100%
BLOCK B
- Block work for ground floor – 100%
- Formwork for first floor slab, beam and staircase – 100%
- Reinforcements for first floor slab, beam and staircase – 100%
- Electrical piping on first floor slab – 100%
- Plumbing piping on first floor slab – 100%
- First floor slab beam and staircase concrete works – 100%
- Reinforcement for first floor extension columns – 100%
- First floor block work – 100%
- Formwork for first floor extension columns/lintels – 100%
- Concrete works on first floor extension columns/lintels – 100%
- Ground floor Electrical piping on walls (internal/external) 100%
- Ground floor Plumbing piping on walls – in progress.
- Ground floor internal plastering – 90%
BLOCK C
- Blockwork for ground floor – 100%
- Formwork for first floor slab, Beam and Staircase – 97%
- Reinforcements for slab, Beam and Staircase – 98%
- Electrical piping on first floor slab – 100%
- Plumbing piping on first floor slab – 100%
BLOCK D
- Block work for ground floor – 100%
- Formwork for first floor slab, beam and staircase – 100%
- Reinforcements for first floor slab, beam and staircase – 100%
- Electrical piping on first floor slab – 100%
- Plumbing piping on first floor slab – 100%
- First floor slab beam and staircase concrete works – 100%
- Reinforcement for first floor extension columns/lintels – 100%
- First floor block work – 100%
- Formwork for first floor extension columns/lintels – 100%
- Concrete works on first floor extension columns/lintels – 100%
- Formwork for second floor slab, beam and staircase – 98%
- Reinforcements for second floor slab, beam and staircase – 100%
- Second floor electrical piping on slab 100%
- Second floor plumbing piping on slab 100%
- Ground floor Plumbing piping on walls – in progress.
- Ground floor electrical piping on walls (internal/external) – 100%
- Ground floor internal plastering – 95%
BLOCK E
- Block work for ground floor – 100%
- Formwork for first floor slab, beam and staircase – 100%
- Reinforcements for first floor slab, beam and staircase – 100%
- Electrical piping on first floor slab – 100%
- Plumbing piping on first floor slab – 100%
- First floor slab beam and staircase concrete works – 100%
- Reinforcement for first floor extension columns/lintels – 100%
- First floor block work – 99%
- Formwork for first floor extension columns/lintels – 100%
- Concrete works on first floor extension columns/lintels – 100%
- Ground floor electrical piping on walls (internal/external) – 100%
- Ground floor Plumbing piping on walls – in progress
- Ground floor Internal plastering – 10%
BLOCK F
- Blockwork for ground floor – 100%
- Formwork for first floor slab, Beam and Staircase – 100%
- Reinforcement for first floor slab, Beam and Staircase – 100%
- Electrical piping on first floor slab – 100%
- Plumbing piping on first floor slab – 100%
- First floor slab beam and staircase concrete works – 100%
- Reinforcement for first floor extension columns/lintels – 100%
- First floor block work – 99%
- Formwork for first floor extension columns/lintels – 100%
- Concrete works on first floor extension columns/lintels – 100%
THANK YOU.