APPENDIX

Block A – Formwork for first floor extension columns/lintels – 100% done.

Block B – First floor block work – 100% done.

Block C – Formwork for first floor slab, Beam and Staircase – 97% done.

Block D – Reinforcements for second floor slab, beam and staircase – 100% done.

Block E – First floor block work – 99% done.

Block F – Concrete works on first floor extension columns/lintels – 100% done.

WORK PROGRESS

BLOCK A
  • Block work for ground floor – 100%
  • Formwork for first floor slab, beam and staircase – 100%
  • Reinforcements for first floor slab, beam and staircase – 100%
  • Electrical piping on first floor slab – 100%
  • Plumbing piping on first floor slab – 100%
  • First floor slab beam and staircase concrete works – 100%
  • Reinforcement for first floor extension columns – 100%
  • First floor block work – 97%
  • Formwork for first floor extension columns/lintels – 100%
  • Concrete works on first floor extension columns/lintels – 100%
BLOCK B
  • Block work for ground floor – 100%
  • Formwork for first floor slab, beam and staircase – 100%
  • Reinforcements for first floor slab, beam and staircase – 100%
  • Electrical piping on first floor slab – 100%
  • Plumbing piping on first floor slab – 100%
  • First floor slab beam and staircase concrete works – 100%
  • Reinforcement for first floor extension columns – 100%
  • First floor block work – 100%
  • Formwork for first floor extension columns/lintels – 100%
  • Concrete works on first floor extension columns/lintels – 100%
  • Ground floor Electrical piping on walls (internal/external) 100%
  • Ground floor Plumbing piping on walls – in progress.
  • Ground floor internal plastering – 90%
BLOCK C
  • Blockwork for ground floor – 100%
  • Formwork for first floor slab, Beam and Staircase – 97%
  • Reinforcements for slab, Beam and Staircase – 98%
  • Electrical piping on first floor slab – 100%
  • Plumbing piping on first floor slab – 100%
BLOCK D
  • Block work for ground floor – 100%
  • Formwork for first floor slab, beam and staircase – 100%
  • Reinforcements for first floor slab, beam and staircase – 100%
  • Electrical piping on first floor slab – 100%
  • Plumbing piping on first floor slab – 100%
  • First floor slab beam and staircase concrete works – 100%
  • Reinforcement for first floor extension columns/lintels – 100%
  • First floor block work – 100%
  • Formwork for first floor extension columns/lintels – 100%
  • Concrete works on first floor extension columns/lintels – 100%
  • Formwork for second floor slab, beam and staircase – 98%
  • Reinforcements for second floor slab, beam and staircase – 100%
  • Second floor electrical piping on slab 100%
  • Second floor plumbing piping on slab 100%
  • Ground floor Plumbing piping on walls – in progress.
  • Ground floor electrical piping on walls (internal/external) – 100%
  • Ground floor internal plastering – 95%

BLOCK E

  • Block work for ground floor – 100%
  • Formwork for first floor slab, beam and staircase – 100%
  • Reinforcements for first floor slab, beam and staircase – 100%
  • Electrical piping on first floor slab – 100%
  • Plumbing piping on first floor slab – 100%
  • First floor slab beam and staircase concrete works – 100%
  • Reinforcement for first floor extension columns/lintels – 100%
  • First floor block work – 99%
  • Formwork for first floor extension columns/lintels – 100%
  • Concrete works on first floor extension columns/lintels – 100%
  • Ground floor electrical piping on walls (internal/external) – 100%
  • Ground floor Plumbing piping on walls – in progress
  • Ground floor Internal plastering – 10%

BLOCK F

  • Blockwork for ground floor – 100%
  • Formwork for first floor slab, Beam and Staircase – 100%
  • Reinforcement for first floor slab, Beam and Staircase – 100%
  • Electrical piping on first floor slab – 100%
  • Plumbing piping on first floor slab – 100%
  • First floor slab beam and staircase concrete works – 100%
  • Reinforcement for first floor extension columns/lintels – 100%
  • First floor block work – 99%
  • Formwork for first floor extension columns/lintels – 100%
  • Concrete works on first floor extension columns/lintels – 100%

THANK YOU.