Arial view of 4 bedroom, 3 bedroom and their Road network.

Picture showing the Bridge.

Lot – 16: Plastering of the whole block – in progress.

Lot – 18-22: Blockwork at ground floor – 100%

Lot – 32-33: Foundation to DPC.

Lot – 17: Reinforcement work – 100% done.

Lot – 26: Blockwork – 100%
WORK SUMMARY
LOT – 16:
- Roof carcass – 100%
- Parapet blockwork – 100%
- External plastering – 100%
LOT – 17:
- Slab formwork – 100%
- Reinforcement work – 100%
- Electrical work – 100%
LOT – 18 -22:
- Blockwork at ground floor – 100%
LOT – 26 & 31:
- Blockwork – 100%
LOT – 27 & 29:
- Blockwork on ground floor – 30%
LOT – 32, & 33:
- Foundation to DPC
ALL F-Ds:
- All Screeded.
- Roadwork stone base completed
- Asphalt work – 100% done.