APPENDIX

Arial view of 4 bedroom, 3 bedroom and their Road network.

Picture showing the Bridge.

 Lot – 16: Plastering of the whole block – in progress.

Lot – 18-22: Blockwork at ground floor – 100%

Lot – 32-33: Foundation to DPC.

Lot – 17: Reinforcement work – 100% done.

Lot – 26: Blockwork – 100%

WORK SUMMARY

LOT – 16:

  • Roof carcass – 100%
  • Parapet blockwork – 100%
  • External plastering – 100%

LOT – 17:

  • Slab formwork – 100%
  • Reinforcement work – 100%
  • Electrical work – 100%

LOT – 18 -22:

  • Blockwork at ground floor – 100%

LOT – 26 & 31:

  • Blockwork – 100%

LOT – 27 & 29:

  • Blockwork on ground floor – 30%

LOT – 32, & 33:

  • Foundation to DPC

ALL F-Ds:

  • All Screeded.
  • Roadwork stone base completed
  • Asphalt work – 100% done.

THANK YOU.