SITE ACTIVITY REPORT FOR THE MONTH OF AUGUST 2022 (COLOR CODE ESTATE PHASE 2, ABUJA)
APPENDIX Lot 1 – Blockwork second floor - 80% done. Lot 2 - Slab Reinforcement second floor – 70% done. Lot 3 - Slab formwork second floor – 30% done. Lot 4 - Block work first floor - 100% done. Lot 5 - Slab formwork second floor - 100% done. [...]