SITE ACTIVITY REPORT FOR THE MONTH OF AUGUST 2021 (COLOR CODE ESTATE, ABUJA)

APPENDIX Block A- Roof electrical pipe works - 40% done.   Block B – Block work to roof beam level - 100% done.   Block C- Roof slab cantilever reinforcements   Block D- Second-floor slab formwork -100% done   WORK PROGRESS Block A. General electrical pipping work [...]

SITE ACTIVITY REPORT FOR THE MONTH OF JULY 2021 (COLOR CODE ESTATE, ABUJA)

APPENDIX Block A- Reinforcement work on roof slab completed   Block B - Blockwork to lintel level   Block C- Roof slab cantilever reinforcements.   WORK PROGRESS Block A. Electrical pipping work – 40% Roof slab Cantilever formwork completed. Reinforcement work on roof slab completed. Electrical work is in [...]

SITE ACTIVITY REPORT FOR THE MONTH OF JULY 2021 (CEDARWOOD CITY, ABUJA)

APPENDIX Picture showing the Screeding level on Lot 15   Retaining wall by the river ongoing   Picture showing the Screeding level on Lot 14   LOT 11- Reinforcement work completed   Lot 12- Copping 100% done   Picture showing Soakaway between Lot 8 [...]

Go to Top