SITE ACTIVITY REPORT FOR THE MONTH OF JULY 2022, (GLENDALE POINT, ABUJA)

APPENDIX Block A - Block work ongoing on ground floor. Block B - Ironwork, Electrical, and Plumbing work on third slab completed. WORK SUMMARY BLOCK A Block work ongoing on ground floor. Forming of formwork for casting on going. BLOCK B Ironwork, electrical, and plumbing work on third slab completed. Block work [...]

SITE ACTIVITY REPORT FOR THE MONTH OF JULY 2022 (COLOR CODE EXTRA, ABUJA)

APPENDIX Block A - Formwork for first floor extension columns/lintels – 100% done. Block B - First floor block work – 100% done. Block C - Formwork for first floor slab, Beam and Staircase – 97% done. Block D - Reinforcements for second floor slab, beam [...]

SITE ACTIVITY REPORT FOR THE MONTH OF OCTOBER 2021 (GLENDALE PEARL, ABUJA)

APPENDIX Fixing/installation of windows 100% done on Block A.   Fixing/installation of windows 80% done on Block B.   Plastering of External wall 100% done on Block C.   Window dressings and fixing of window grooves 100% done on Block D.   Picture showing the complete [...]

Go to Top