APPENDIX
Block A – Internal Finishing – in progress
Block B – General external maintenance – In progress.
Block C – General external maintenance – in progress.
Block D – General external maintenance/screening – in progress.
Casting of walls of cesspool done.
WORK PROGRESS
Block A.
- Electrical lighting point works – ongoing.
- Electrical work – ongoing.
- External maintenance – progress. CT
- Internal Finishing – in progress.
Block B.
- General external maintenance – In progress.
Block C.
- Plumbing work – In progress
- Electrical work wiring of light point – ongoing.
- General internal plastering – 100%
- General external maintenance – in progress.
- Internal works – ongoing.
Block D.
- Internal plastering – 100%
- Internal maintenance – in progress
- General external maintenance/screening – in progress.
- Cesspool construction in progress.
- Casting of walls of cesspool done.
- Formwork for the casting of cesspool slab in progress.