APPENDIX

Block A – First floor block work – 99% done.

Block B – Formwork for second floor slab, beam and staircase – 45% done.

Block C – Concrete works on first floor slab, beam and staircase – 100% done.

Block D – Formwork for 2nd floor slab, beam and staircase 100% done.

Block E – Formwork for first floor extension columns/lintels – 100%

Block F – First floor block work – 99% done.

WORK PROGRESS

BLOCK A

  • Block work for ground floor – 100%
  • Formwork for first floor slab, beam and staircase – 100%
  • Reinforcements for first floor slab, beam and staircase – 100%
  • Electrical piping on first floor slab – 100%
  • Plumbing piping on first floor slab – 100%
  • First floor slab beam and staircase concrete works – 100%
  • Reinforcement for first floor extension columns – 100 %
  • First floor block work – 99%
  • Formwork for first floor extension columns/lintels – 100%
  • Concrete works on first floor extension columns/lintels – 100%

BLOCK B

  • Block work for ground floor – 100%
  • Formwork for first floor slab, beam and staircase – 100%
  • Reinforcements for first floor slab, beam and staircase – 100%
  • Electrical piping on first floor slab – 100%
  • Plumbing piping on first floor slab 100%
  • First floor slab beam and staircase concrete works – 100%
  • Reinforcement for first floor extension columns – 100%
  • First floor block work – 100%
  • Formwork for first floor extension columns/lintels – 100%
  • Concrete works on first floor extension columns and lintels – 100%
  • Ground floor Electrical piping on walls (internal/external) – 100%
  • Ground floor Plumbing piping on walls – 100%
  • Ground floor Internal plastering – 90%
  • Formwork for second floor slab, beam and staircase – 45%

BLOCK C

  • Block work for ground floor – 100%
  • Formwork for first floor slab, beam and staircase – 100%
  • Reinforcements for first floor slab, beam and staircase – 100%
  • Electrical piping on first floor slab – 100%
  • Plumbing piping on first floor slab – 100%
  • Concrete works on first floor slab, beam and staircase – 100%
  • Block work on first floor slab – 35%

BLOCK D

  • Block work for ground floor – 100%
  • Formwork for first floor slab, beam and staircase – 100%
  • Reinforcements for first floor slab, beam and staircase – 100%
  • Electrical piping on first floor slab – 100%
  • Plumbing piping on first floor slab – 100%
  • 1st floor slab beam and staircase concrete works – 100%
  • Reinforcement for first floor extension columns/lintels – 100%
  • 1st floor block work – 100%
  • Formwork for first floor extension columns/lintels – 100%
  • Concrete works on first floor extension columns/lintels – 100%
  • Formwork for 2nd floor slab, beam and staircase 100%
  • Reinforcements for second floor slab, beam and staircase – 100%
  • Electrical piping on second floor slab – 100%
  • Plumbing piping on Second floor slab – 100%
  • Concrete works on second floor slab, beam and staircase – 100%
  • Ground floor plumbing piping on walls – 100%
  • Ground floor electrical piping on walls (internal/external) – 100%
  • Ground floor internal plastering – 95%
  • Block work on second floor slab – 45%

BLOCK E

  • Block work for ground floor – 100%
  • Formwork for first floor slab, beam and staircase – 100%
  • Reinforcements for first floor slab, beam and staircase – 100%
  • Electrical piping on 1st floor slab – 100%
  • Plumbing piping on first floor slab – 100%
  • First floor slab, beam and staircase concrete works – 100%
  • Reinforcement for first floor extension columns/lintels – 100%
  • First floor block work – 99%
  • Formwork for first floor extension columns/lintels – 100%
  • Concrete works on first floor extension columns/lintels – 100%
  • Ground floor electrical piping on walls (internal/external) – 100%
  • Ground floor plumbing piping on walls – 100%
  • Ground floor internal plastering – 80%

BLOCK F

  • Block work for ground floor – 100%
  • Formwork for first floor slab, beam and staircase – 100%
  • Reinforcements for first floor slab, beam and staircase – 100%
  • Electrical piping on first floor slab – 100%
  • Plumbing piping on first floor slab – 100%
  • First floor slab, beam and staircase concrete works – 100%
  • Reinforcement for first floor extension columns/lintels – 100%
  • First floor block work – 99%
  • Formwork for first floor extension columns/lintels – 100%
  • Concrete works on first floor extension columns/lintels – 100%
  • Electrical piping for dropping on ground floor – 100%
  • Ground floor Plumbing piping on walls – 100%

THANK YOU.