APPENDIX
Block A – First floor block work – 99% done.
Block B – Formwork for second floor slab, beam and staircase – 45% done.
Block C – Concrete works on first floor slab, beam and staircase – 100% done.
Block D – Formwork for 2nd floor slab, beam and staircase 100% done.
Block E – Formwork for first floor extension columns/lintels – 100%
Block F – First floor block work – 99% done.
WORK PROGRESS
BLOCK A
- Block work for ground floor – 100%
- Formwork for first floor slab, beam and staircase – 100%
- Reinforcements for first floor slab, beam and staircase – 100%
- Electrical piping on first floor slab – 100%
- Plumbing piping on first floor slab – 100%
- First floor slab beam and staircase concrete works – 100%
- Reinforcement for first floor extension columns – 100 %
- First floor block work – 99%
- Formwork for first floor extension columns/lintels – 100%
- Concrete works on first floor extension columns/lintels – 100%
BLOCK B
- Block work for ground floor – 100%
- Formwork for first floor slab, beam and staircase – 100%
- Reinforcements for first floor slab, beam and staircase – 100%
- Electrical piping on first floor slab – 100%
- Plumbing piping on first floor slab 100%
- First floor slab beam and staircase concrete works – 100%
- Reinforcement for first floor extension columns – 100%
- First floor block work – 100%
- Formwork for first floor extension columns/lintels – 100%
- Concrete works on first floor extension columns and lintels – 100%
- Ground floor Electrical piping on walls (internal/external) – 100%
- Ground floor Plumbing piping on walls – 100%
- Ground floor Internal plastering – 90%
- Formwork for second floor slab, beam and staircase – 45%
BLOCK C
- Block work for ground floor – 100%
- Formwork for first floor slab, beam and staircase – 100%
- Reinforcements for first floor slab, beam and staircase – 100%
- Electrical piping on first floor slab – 100%
- Plumbing piping on first floor slab – 100%
- Concrete works on first floor slab, beam and staircase – 100%
- Block work on first floor slab – 35%
BLOCK D
- Block work for ground floor – 100%
- Formwork for first floor slab, beam and staircase – 100%
- Reinforcements for first floor slab, beam and staircase – 100%
- Electrical piping on first floor slab – 100%
- Plumbing piping on first floor slab – 100%
- 1st floor slab beam and staircase concrete works – 100%
- Reinforcement for first floor extension columns/lintels – 100%
- 1st floor block work – 100%
- Formwork for first floor extension columns/lintels – 100%
- Concrete works on first floor extension columns/lintels – 100%
- Formwork for 2nd floor slab, beam and staircase 100%
- Reinforcements for second floor slab, beam and staircase – 100%
- Electrical piping on second floor slab – 100%
- Plumbing piping on Second floor slab – 100%
- Concrete works on second floor slab, beam and staircase – 100%
- Ground floor plumbing piping on walls – 100%
- Ground floor electrical piping on walls (internal/external) – 100%
- Ground floor internal plastering – 95%
- Block work on second floor slab – 45%
BLOCK E
- Block work for ground floor – 100%
- Formwork for first floor slab, beam and staircase – 100%
- Reinforcements for first floor slab, beam and staircase – 100%
- Electrical piping on 1st floor slab – 100%
- Plumbing piping on first floor slab – 100%
- First floor slab, beam and staircase concrete works – 100%
- Reinforcement for first floor extension columns/lintels – 100%
- First floor block work – 99%
- Formwork for first floor extension columns/lintels – 100%
- Concrete works on first floor extension columns/lintels – 100%
- Ground floor electrical piping on walls (internal/external) – 100%
- Ground floor plumbing piping on walls – 100%
- Ground floor internal plastering – 80%
BLOCK F
- Block work for ground floor – 100%
- Formwork for first floor slab, beam and staircase – 100%
- Reinforcements for first floor slab, beam and staircase – 100%
- Electrical piping on first floor slab – 100%
- Plumbing piping on first floor slab – 100%
- First floor slab, beam and staircase concrete works – 100%
- Reinforcement for first floor extension columns/lintels – 100%
- First floor block work – 99%
- Formwork for first floor extension columns/lintels – 100%
- Concrete works on first floor extension columns/lintels – 100%
- Electrical piping for dropping on ground floor – 100%
- Ground floor Plumbing piping on walls – 100%
THANK YOU.