APPENDIX
![1](https://whiteavenuegroup.com/wp-content/uploads/2022/08/1-2-300x225.jpg)
Lot 1 – Blockwork second floor – 80% done.
![2](https://whiteavenuegroup.com/wp-content/uploads/2022/08/2-2-300x225.jpg)
Lot 2 – Slab Reinforcement second floor – 70% done.
![3](https://whiteavenuegroup.com/wp-content/uploads/2022/08/3-2-300x225.jpg)
Lot 3 – Slab formwork second floor – 30% done.
![4](https://whiteavenuegroup.com/wp-content/uploads/2022/08/4-2-300x225.jpg)
Lot 4 – Block work first floor – 100% done.
![5](https://whiteavenuegroup.com/wp-content/uploads/2022/08/5-2-300x225.jpg)
Lot 5 – Slab formwork second floor – 100% done.
WORK SUMMARY
Lot 1
- Blockwork second floor – 80%
- Ground Floor Slab – 100%
- Slab Reinforcement on first floor – 100%
- Slab formwork to first floor – 100%
- Blockwork at Basement – 100%
- Blockwork on Ground Floor – 100%
Lot 2
- Formwork for Slab on first floor – 100%
- Block work at first Floor – 100%
- Block work on ground floor – 100%
- Plumbing / Mechanical – 80%
- Slab Reinforcement second floor – 70%
Lot 3
- Blockwork on first floor – 100%
- Slab Reinforcement on Ground floor – 100%
- Plumbing /mechanical – 100%
- Blockwork at Ground floor – 100%
- Slab formwork second floor – 30%
Lot 4
- Block work first floor – 100%
- Block work second floor – in progress.
- Slab Reinforcement on ground floor – 100%
- Slab formwork on Ground floor – 50%
- Block work on ground floor – 100%
Lot 5
- Formwork for Slab on first Floor – 100%
- Blockwork on first floor – 100%
- Blockwork on ground floor – 100%
- Slab formwork second floor – 100%
THANK YOU