APPENDIX

 Lot 1 – Blockwork second floor – 80% done.

Lot 2 – Slab Reinforcement second floor – 70% done.

Lot 3 – Slab formwork second floor – 30% done.

Lot 4 Block work first floor – 100% done.

Lot 5 – Slab formwork second floor – 100% done.

WORK SUMMARY

Lot 1

  • Blockwork second floor – 80%
  • Ground Floor Slab – 100%
  • Slab Reinforcement on first floor – 100%
  • Slab formwork to first floor – 100%
  • Blockwork at Basement – 100%
  • Blockwork on Ground Floor – 100%

Lot 2

  • Formwork for Slab on first floor – 100%
  • Block work at first Floor – 100%
  • Block work on ground floor – 100%
  • Plumbing / Mechanical – 80%
  • Slab Reinforcement second floor – 70%

Lot 3

  • Blockwork on first floor – 100%
  • Slab Reinforcement on Ground floor – 100%
  • Plumbing /mechanical – 100%
  • Blockwork at Ground floor – 100%
  • Slab formwork second floor – 30%

Lot 4

  • Block work first floor – 100%
  • Block work second floor – in progress.
  • Slab Reinforcement on ground floor – 100%
  • Slab formwork on Ground floor – 50%
  • Block work on ground floor – 100%

Lot 5

  • Formwork for Slab on first Floor – 100%
  • Blockwork on first floor – 100%
  • Blockwork on ground floor – 100%
  • Slab formwork second floor – 100%

THANK YOU