Block A – Formwork to third Floor completed.
![22](https://whiteavenuegroup.com/wp-content/uploads/2022/08/22-300x225.jpg)
Block B – Formwork to roof beam ongoing.
WORK SUMMARY
BLOCK A
- Formwork to third Floor completed.
- Ironwork and plumbing / Electrical on going.
BLOCK B
- Third suspended slab casted.
- Extension column casted.
- Form work to roof beam ongoing.