APPENDIX

Arial view of 4 bedroom, 3 bedroom and their Road network.

Picture showing the Bridge.

Lot – 16: Roof carcass – 100% done.

Lot – 18-22: Blockwork at ground floor – 100% done.

Lot – 32-33: Backfilling – 100% done.

Lot – 17: First floor Blockwork – 30% done.

Lot – 26: Blockwork on ground floor – 100%.

CESSPOOL – 75% done.

WORK SUMMARY 

LOT – 16:

  • Roof carcass – 100%
  • Parapet blockwork – 100%
  • External plastering – 100%
  • Internal electrical piping – 50%

LOT – 17:

  • Slab formwork – 100%
  • Reinforcement work – 100%
  • Electrical work – 100%
  • slab casting – 67%
  • First floor Block work – 30%

LOT – 18 -22:

  • Blockwork at ground floor – 100%


LOT- 19-20

  • Block work at ground floor 30%

LOT – 26, 29 & 31:

  • Blockwork at ground floor – 100%

LOT – 27

  • Blockwork on ground floor – 30%

LOT – 30

  • Foundation Blockwork – 100%
  • Block hole casting – 100%
  • Backfilling – 70%
  • DPC hardcore – 35%

LOT – 32

  • Foundation Blockwork – 100%
  • Block hole casting – 100%
  • Backfilling – 100%
  • DPC hardcore – 40%

LOT 33

  • Foundation Blockwork – 100%
  • Block hole casting – 100%
  • Backfilling – 100%
  • DPC hardcore – In progress.

ALL F-Ds:

  • All Screeded.
  • Roadwork stone base completed
  • Asphalt work – 100% done.                       

CESSPOOL – 75%

CONNECTION TO SEWER – 15%

 

                                                                    THANK YOU.