Lot – 16: Roof carcass – 100% done.
![4](https://whiteavenuegroup.com/wp-content/uploads/2022/08/4-1-300x225.jpg)
Lot – 18-22: Blockwork at ground floor – 100% done.
![5](https://whiteavenuegroup.com/wp-content/uploads/2022/08/5-1-300x225.jpg)
Lot – 32-33: Backfilling – 100% done.
![6](https://whiteavenuegroup.com/wp-content/uploads/2022/08/6-1-300x225.jpg)
Lot – 17: First floor Blockwork – 30% done.
![7](https://whiteavenuegroup.com/wp-content/uploads/2022/08/7-300x225.jpg)
Lot – 26: Blockwork on ground floor – 100%.
![8](https://whiteavenuegroup.com/wp-content/uploads/2022/08/8-300x225.jpg)
CESSPOOL – 75% done.
WORK SUMMARY
LOT – 16:
- Roof carcass – 100%
- Parapet blockwork – 100%
- External plastering – 100%
- Internal electrical piping – 50%
LOT – 17:
- Slab formwork – 100%
- Reinforcement work – 100%
- Electrical work – 100%
- slab casting – 67%
- First floor Block work – 30%
LOT – 18 -22:
- Blockwork at ground floor – 100%
LOT- 19-20
- Block work at ground floor 30%
LOT – 26, 29 & 31:
- Blockwork at ground floor – 100%
LOT – 27
- Blockwork on ground floor – 30%
LOT – 30
- Foundation Blockwork – 100%
- Block hole casting – 100%
- Backfilling – 70%
- DPC hardcore – 35%
LOT – 32
- Foundation Blockwork – 100%
- Block hole casting – 100%
- Backfilling – 100%
- DPC hardcore – 40%
LOT 33
- Foundation Blockwork – 100%
- Block hole casting – 100%
- Backfilling – 100%
- DPC hardcore – In progress.
ALL F-Ds:
- All Screeded.
- Roadwork stone base completed
- Asphalt work – 100% done.
CESSPOOL – 75%
CONNECTION TO SEWER – 15%