SITE ACTIVITY REPORT FOR THE MONTH OF AUGUST 2022 (CEDARWOOD CITY, ABUJA)
APPENDIX Arial view of 4 bedroom, 3 bedroom and their Road network. Picture showing the Bridge. Lot – 16: Roof carcass – 100% done. Lot – 18-22: Blockwork at ground floor – 100% done. Lot – 32-33: Backfilling - 100% done. Lot – 17: First floor Blockwork - 30% [...]