SITE ACTIVITY REPORT FOR THE MONTH OF AUGUST 2022 (COLOR CODE EXTRA, ABUJA)
APPENDIX Block A - First floor block work - 99% done. Block B - Formwork for second floor slab, beam and staircase - 45% done. Block C - Concrete works on first floor slab, beam and staircase - 100% done. Block D - Formwork for 2nd [...]