APPENDIX

Lot 1 – Slab Reinforcement on first floor – 100% done.

Lot 2 – Formwork for Slab on first floor – 90% done.

Lot 3 – Slab Reinforcement on Ground floor – 100% done.

Lot 4 – Slab formwork on Ground floor – 50% done.

Lot 5 – Formwork for Slab on first Floor – 20% done.

WORK SUMMARY

Lot 1

  • Commencement of Blockwork.
  • Ground Floor Slab – 100%.
  • Mechanical work – 100%.
  • Electrical work – 100%.
  • Slab Reinforcement on first floor – 100%
  • Slab formwork to first floor – 100%.
  • Blockwork @ Basement completed – 100%
  • Blockwork on Ground Floor completed – 100%

Lot 2

  • Formwork for Slab on first floor – 90%
  • Block work at first Floor completed – 100%
  • Block work on ground floor completed – 100%
  • Plumbing / Mechanical – 80%

Lot 3

  • Blockwork on first floor – 100%
  • Slab Reinforcement on Ground floor – 100%
  • Plumbing /mechanical – 100%
  • Electrical – 100%
  • Blockwork at Ground floor – 100%

Lot 4

  • Block work – 80%
  • Slab Reinforcement on ground floor – 100%
  • Mechanical fittings – 100%.
  • Electrical fittings – 90%
  • Slab formwork on Ground floor – 50%
  • Block work on ground floor – 100%

Lot 5

  • Formwork for Slab on first Floor – 20%
  • Blockwork on first floor – 100%.
  • Slab Reinforcement / wood formwork – 100%
  • Mechanical work – 100%
  • Electrical – 100%
  • Blockwork on ground floor completed – 100%

THANK YOU