APPENDIX
Lot 1 – Slab Reinforcement on first floor – 100% done.
Lot 2 – Formwork for Slab on first floor – 90% done.
Lot 3 – Slab Reinforcement on Ground floor – 100% done.
Lot 4 – Slab formwork on Ground floor – 50% done.
Lot 5 – Formwork for Slab on first Floor – 20% done.
WORK SUMMARY
Lot 1
- Commencement of Blockwork.
- Ground Floor Slab – 100%.
- Mechanical work – 100%.
- Electrical work – 100%.
- Slab Reinforcement on first floor – 100%
- Slab formwork to first floor – 100%.
- Blockwork @ Basement completed – 100%
- Blockwork on Ground Floor completed – 100%
Lot 2
- Formwork for Slab on first floor – 90%
- Block work at first Floor completed – 100%
- Block work on ground floor completed – 100%
- Plumbing / Mechanical – 80%
Lot 3
- Blockwork on first floor – 100%
- Slab Reinforcement on Ground floor – 100%
- Plumbing /mechanical – 100%
- Electrical – 100%
- Blockwork at Ground floor – 100%
Lot 4
- Block work – 80%
- Slab Reinforcement on ground floor – 100%
- Mechanical fittings – 100%.
- Electrical fittings – 90%
- Slab formwork on Ground floor – 50%
- Block work on ground floor – 100%
Lot 5
- Formwork for Slab on first Floor – 20%
- Blockwork on first floor – 100%.
- Slab Reinforcement / wood formwork – 100%
- Mechanical work – 100%
- Electrical – 100%
- Blockwork on ground floor completed – 100%