APPENDIX

Block A – Block work ongoing on ground floor.

Block B – Ironwork, Electrical, and Plumbing work on third slab completed.

WORK SUMMARY

BLOCK A

  • Block work ongoing on ground floor.
  • Forming of formwork for casting on going.

BLOCK B

  • Ironwork, electrical, and plumbing work on third slab completed.
  • Block work on second slab – 80%.