APPENDIX

Block A – Block work ongoing on ground floor.

Block B – Ironwork, Electrical, and Plumbing work on third slab completed.
WORK SUMMARY
BLOCK A
- Block work ongoing on ground floor.
- Forming of formwork for casting on going.
BLOCK B
- Ironwork, electrical, and plumbing work on third slab completed.
- Block work on second slab – 80%.