APPENDIX

Block A – Installation of sliding doors on second floor door – Done.

Block B – Parapet plastering / Dressing of copping – Done.

Block C – Fixing of windows – Done.

Block D – Fixing of Front / Back doors – Done.

Cesspool construction in progress.

WORK PROGRESS

Block A.

  • Roof covering/Flashings – Completed.
  • External Screeding – 95%
  • Internal Plastering – Done.
  • Plumbing work – 95%
  • Electrical work – 95%
  • External maintenance – In progress.
  • Fixing of Front / Back doors – Done.
  • Fixing of windows – Done.
  • Installation of sliding doors on second floor door – Done.
  • Installation of Maid room doors – Done.

Block B.

  • External plastering – 90%
  • Internal plastering – Done.
  • Parapet plastering / Dressing of copping – Done.
  • Roof covering – Done.
  • General external maintenance – In progress.
  • Fixing of Front / Back doors – Done.
  • Fixing of windows – Done.
  • Installation of sliding doors on second floor door – Done.
  • Installation of Maid room doors – Done.

Block C.

  • External Screeding – 95%
  • Plumbing work – 95%
  • Electrical work – 95%
  • General internal plastering – 95%
  • General external maintenance – Completed.
  • Fixing of Front / Back doors – Done.
  • Fixing of windows – Done.
  • Installation of sliding doors on second floor door – Done.
  • Installation of Maid room doors – Done.

Block D.

  • Parapet Blockwork / plastering – 100%
  • External plastering – 95%
  • Internal plastering – 90%
  • Roof trusses work – 100%
  • Roof covering – Done.
  • General external maintenance – In progress.
  • Fixing of Front / Back doors – Done.
  • Fixing of windows – Done.
  • Installation of sliding doors on second floor door – Done.
  • Installation of Maid room doors – Done.

Cesspool construction in progress.

Main Gate installation in progress.

                                                                                                                      THANK YOU.