APPENDIX
Block A – Installation of sliding doors on second floor door – Done.
Block B – Parapet plastering / Dressing of copping – Done.
Block C – Fixing of windows – Done.
Block D – Fixing of Front / Back doors – Done.
Cesspool construction in progress.
WORK PROGRESS
Block A.
- Roof covering/Flashings – Completed.
- External Screeding – 95%
- Internal Plastering – Done.
- Plumbing work – 95%
- Electrical work – 95%
- External maintenance – In progress.
- Fixing of Front / Back doors – Done.
- Fixing of windows – Done.
- Installation of sliding doors on second floor door – Done.
- Installation of Maid room doors – Done.
Block B.
- External plastering – 90%
- Internal plastering – Done.
- Parapet plastering / Dressing of copping – Done.
- Roof covering – Done.
- General external maintenance – In progress.
- Fixing of Front / Back doors – Done.
- Fixing of windows – Done.
- Installation of sliding doors on second floor door – Done.
- Installation of Maid room doors – Done.
Block C.
- External Screeding – 95%
- Plumbing work – 95%
- Electrical work – 95%
- General internal plastering – 95%
- General external maintenance – Completed.
- Fixing of Front / Back doors – Done.
- Fixing of windows – Done.
- Installation of sliding doors on second floor door – Done.
- Installation of Maid room doors – Done.
Block D.
- Parapet Blockwork / plastering – 100%
- External plastering – 95%
- Internal plastering – 90%
- Roof trusses work – 100%
- Roof covering – Done.
- General external maintenance – In progress.
- Fixing of Front / Back doors – Done.
- Fixing of windows – Done.
- Installation of sliding doors on second floor door – Done.
- Installation of Maid room doors – Done.
Cesspool construction in progress.
Main Gate installation in progress.
THANK YOU.