Phase 1 Report
WORK SUMMARY
LOT – 11: ROOF BEAM:
- Formwork – 100%
- Reinforcement work –100%
- Parapet wall – 75%
- Internal rendering – ongoing.
- Electrical piping work – ongoing.
- External rendering ongoing.
LOT – 12: ROOF BEAM:
- Formwork – 100%
- Reinforcement – 100%
- Casting – 100%
- Parapet wall – 100%
- Electrical piping – 100%
- Parapet boarding and casting – 80%
- External rendering ongoing.
LOT – 14
- Colum boarding and casting – 80%
- Tie beam on two flat (to balance up with the basement side).
- Formwork – 100%
- Ironwork – 100%
- Casting – 100%
LOT – 15: ROOF BEAM:
- Formwork – 100%
- Reinforcement work – 100%
- Parapet blockwork – 100%
- Parapet column boarding and casting – 100%
- External rendering ongoing.
LOT – 16
- Slab casting – 100% (just little recess to balance up).
- Blockwork – 98%
- Column boarding and casting – 85%
FD – 1-6:
- Column boarding and casting – 95%
FD – 9:
- 3 angle dressing – 85%
FD – 1-6:
- Roof beam preparation ongoing.
REINFORCEMENT WALL ALONG LOT 4-6:
- Boarding – 100%
- Casting – 50%
We suspended work because of lack of cement.
GATEHOUSE:
- Casting of the remaining columns – 100%
- Blockwork in between the columns – 100%
- Fabrication ongoing.
GENERAL WORKS
- Fence wall along theme park (blockwork).
- Back filling at the back of lot 3.
- Bridge wall leveling boarding (completed) waiting for casting
APPENDIX
LOT 11- Reinforcement work completed.
Lot 12- Parapet wall is 100% done.
Lot 14- ironwork is 100% done.
Picture showing the bridge.
Picture showing the park.
Picture showing water fountain.
Picture showing the gatehouse.