Phase 1 Report

APPENDIX

Picture showing the Screeding level on Lot 5

Picture showing the Screeding level on Lot6.

LOT 11- Reinforcement work completed.

Lot 12- Parapet wall is 100% done

Retaining wall Cast by fence line

A picture showing Lot 13

Picture of the Sport Center

Picture showing the Bridge

A picture of F-D 1-4

A picture of F-D 5-9

Picture showing the Park

Picture showing water Fountain

Picture showing the Gatehouse

WORK SUMMARY

LOT – 5:

  • Screeding level – 95%

 

LOT – 6:

  • Screeding level – 90%

LOT – 7:

  • Window dressing and divider Wall – 95%
  • Screeding level – 70%

LOT – 11: ROOF BEAM:                                                                                                                                                                                                                                      

  • Formwork – 100%
  • Reinforcement work –100%
  • Roof beam Casting – 100%
  • External rendering (Plastering) – 95%
  • Screeding level – 100%

LOT – 12: ROOF BEAM:

  • Formwork – 100%
  • Reinforcement – 100%
  • Casting – 100%
  • Parapet wall – 100%
  • Electrical piping – 100%
  • Parapet boarding and casting – 80%
  • Grooves – 90%
  • External screeding – 100%
  • Copping – 30%

 

LOT – 14

  • Colum boarding and casting – 80%
  • Tie beam on two flats (To balance up with the Basement side).
  • Formwork – 100%
  • Ironwork – 100%
  • Casting – 100%
  • Bamboo Scaffolding – 85%
  • Roof beam casting ongoing.
  • Basement and ground floor plastering – 100%

LOT – 15: ROOF BEAM:

  • Formwork – 100%
  • Reinforcement work – 100%
  • Parapet blockwork – 100%
  • Parapet column boarding and casting – 100%
  • External rendering (Plastering) – 95%
  • Grooves – 70%
  • Screeding level – 100%

LOT – 16

  • Slab casting – 100% (Just a little Recess to Balance up).
  • Blockwork – 98%
  • Column boarding and casting – 97%
  • Grooves – 100%

FD – 1-3:

  • Screeding level – 100%
  • Bamboo Scaffolding – 100%.

 

FD – 4:

  • External rendering and RB casted.

 

FD –   5: 

  • Roof beam casting – 100%
  • Parapet blockwork – 60%

 

FD –   6: 

  • Formwork – 80%

 

GATEHOUSE:

  • Casting of the remaining columns – 100%
  • Blockwork in between the columns – 100%
  • Arc formwork – 100%

RETAINING WALL: Casted by the fence line.

GENERAL WORKS

  • Fence wall along theme park (blockwork).
  • Backfilling at the back of lot 3.
  • Bridge wall leveling boarding (completed) waiting for casting.

                                                                                                                                         THANK YOU.