Phase 1 Report
APPENDIX
WORK SUMMARY
LOT – 5:
- Screeding level – 95%
LOT – 6:
- Screeding level – 90%
LOT – 7:
- Window dressing and divider Wall – 95%
- Screeding level – 70%
LOT – 11: ROOF BEAM:
- Formwork – 100%
- Reinforcement work –100%
- Roof beam Casting – 100%
- External rendering (Plastering) – 95%
- Screeding level – 100%
LOT – 12: ROOF BEAM:
- Formwork – 100%
- Reinforcement – 100%
- Casting – 100%
- Parapet wall – 100%
- Electrical piping – 100%
- Parapet boarding and casting – 80%
- Grooves – 90%
- External screeding – 100%
- Copping – 30%
LOT – 14
- Colum boarding and casting – 80%
- Tie beam on two flats (To balance up with the Basement side).
- Formwork – 100%
- Ironwork – 100%
- Casting – 100%
- Bamboo Scaffolding – 85%
- Roof beam casting ongoing.
- Basement and ground floor plastering – 100%
LOT – 15: ROOF BEAM:
- Formwork – 100%
- Reinforcement work – 100%
- Parapet blockwork – 100%
- Parapet column boarding and casting – 100%
- External rendering (Plastering) – 95%
- Grooves – 70%
- Screeding level – 100%
LOT – 16
- Slab casting – 100% (Just a little Recess to Balance up).
- Blockwork – 98%
- Column boarding and casting – 97%
- Grooves – 100%
FD – 1-3:
- Screeding level – 100%
- Bamboo Scaffolding – 100%.
FD – 4:
- External rendering and RB casted.
FD – 5:
- Roof beam casting – 100%
- Parapet blockwork – 60%
FD – 6:
- Formwork – 80%
GATEHOUSE:
- Casting of the remaining columns – 100%
- Blockwork in between the columns – 100%
- Arc formwork – 100%
RETAINING WALL: Casted by the fence line.
GENERAL WORKS
- Fence wall along theme park (blockwork).
- Backfilling at the back of lot 3.
- Bridge wall leveling boarding (completed) waiting for casting.
THANK YOU.