APPENDIX

Fixing/installation of windows 100% done on Block A.

Fixing/installation of windows 80% done on Block B.

Plastering of External wall 100% done on Block C.

Window dressings and fixing of window grooves 100% done on Block D.

Picture showing the complete fixing of windows on Block E
SUMMARY
BLOCK A
- Fixing of electrical cables (Wiring) – 60% done.
- Installation of Pop (Polysterene) Ceiling – 25% done.
- Window dressings and fixing of Window grooves – 100% done.
- External wall screeding – In view.
BLOCK B
- Fixing of electrical cables (Wiring) – 60% done.
- Plastering of internal wall – 90% done.
- Fixing of wall skirtings and grooves – 90% done.
- Installation of POP (polysterene) Ceiling – 25% done.
- Fixing/installation of windows – 80% done.
- Window dressing and fixing of window grooves – In view.
- External wall screeding – In view.
BLOCK C
- Plastering of Internal wall – 100% done.
- Plastering of External wall – 100% done.
- Fixing of wall skirting’s and grooves – 80% done.
- Window dressings and fixing of window grooves – In view.
BLOCK D
- Fixing of electrical cables (Wiring) – 60% done.
- Installation of Pop Ceiling – 50% done.
- Window dressings and fixing of windows grooves – 80% done.
- External wall screeding – In view
BLOCK E
- Plastering of internal wall – 95% done.
- Window dressings and Fixing of window grooves – 60% done.
- Installation of POP Ceiling – In view.
SUMMARY OF STATE OF WORK
- Plastering of internal wall 100% done on Block A.
- Setting of partition wall 100% done on Block B
- Roof trusses installation 100% done Block B.
- Formwork and shuttering to third floor slab 100% done on Block C.
- Reinforcement to third floor slab 100% done on Block C.
- Plumbing works on each floor 100% done on Block D.
- Roofing (step tiles installation) 100% done on Block E.
THANK YOU.