SITE ACTIVITY REPORT FOR THE MONTH OF JULY 2022 (CEDARWOOD CITY, ABUJA)

APPENDIX Arial view of 4 bedroom, 3 bedroom and their Road network. Picture showing the Bridge.  Lot – 16: Plastering of the whole block – in progress. Lot – 18-22: Blockwork at ground floor – 100% Lot – 32-33: Foundation to DPC. Lot – 17: Reinforcement work – 100% [...]

SITE ACTIVITY REPORT FOR THE MONTH OF JULY 2022 (COLOR CODE, JAHI, ABUJA)

APPENDIX Exterior plastering - 100% done.        WORK PROGRESSExterior plastering - 100%Internal plastering - 30%Electrical piping - 70%Water tank stand construction - 25%Internal plumbing works - 70%                                                                           THANK YOU.

By |2022-07-28T12:59:27+00:00July 28th, 2022|Uncategorized|0 Comments

SITE ACTIVITY REPORT FOR THE MONTH OF JULY 2022 (COLOR CODE ESTATE PHASE 1, ABUJA)

APPENDIX Block A – POP/ screeding - in progress. Block B - General external maintenance – In progress. Block C - General external maintenance – in progress. Block D - Internal maintenance -  in progress. Casting of walls of cesspool done. WORK PROGRESS Block A. POP/ screeding - in [...]

SITE ACTIVITY REPORT FOR THE MONTH OF JULY 2022, (GLENDALE POINT, ABUJA)

APPENDIX Block A - Block work ongoing on ground floor. Block B - Ironwork, Electrical, and Plumbing work on third slab completed. WORK SUMMARY BLOCK A Block work ongoing on ground floor. Forming of formwork for casting on going. BLOCK B Ironwork, electrical, and plumbing work on third slab completed. Block work [...]